Construction Schedule

June 28 - Milling at Hussman, Mill, High School Street and Virginia Ranch Road

June 29 - Patch paving at Chichester, West Aylesbury Court, Windsor Court, Wendover Court, and Marion Russell Bulb 1 and 2

June 30 - Patch paving continued, and remove tree roots

July 1 - Petromat and paving Hussman, Hill and High School streets

July 2 - Petromat and paving at Virginia Ranch Road

July 6 - Raise utilities

July 7 - Finish utilities, final cleanup