Gardnerville road maintenance starts Monday

Share this: Email | Facebook | X

Staff Reports

Gardnerville is conducting road maintenance starting Monday and lasting through July 7.

During construction hours streets may be closed.

Residents who need to leave or return between 7:30 a.m. and 6 p.m. may need to park their vehicles outside the construction zone.

Residents will be able to get to their homes after 6 p.m.

Construction Schedule

June 28 - Milling at Hussman, Mill, High School Street and Virginia Ranch Road

June 29 - Patch paving at Chichester, West Aylesbury Court, Windsor Court, Wendover Court, and Marion Russell Bulb 1 and 2

June 30 - Patch paving continued, and remove tree roots

July 1 - Petromat and paving Hussman, Hill and High School streets

July 2 - Petromat and paving at Virginia Ranch Road

July 6 - Raise utilities

July 7 - Finish utilities, final cleanup

Comments

Use the comment form below to begin a discussion about this content.

Sign in to comment