 BEFORE THE PUBLIC UTILITIES COMMISSION OF NEVADA 

NOTICE OF JOINT APPLICATION 

AND 

PREHEARING CONFERENCE 

On May 31, 2024, Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy (collectively, “NV Energy”) filed with the Public Utilities Commission of Nevada (“Commission”) a joint application, designated as Docket No. 24-¬05041 (“Joint Application”), for approval of its 2025-2044 Triennial Integrated Resource Plan and 2025-2027 Energy Supply Plan. 

This Notice serves only to notify the public that the Commission has received the above-referenced filing. It is the responsibility of interested persons to review the filing and monitor the proceedings to determine their desired levels of involvement based on how this matter may affect their unique situations. The details provided within this Notice are for informational purposes only and are not meant to be an all-inclusive overview of the filing. The Commission may consider and adopt alternative proposals not contained within the filing, but which are related to the subject matter of the filing and supported by substantial evidence. 

NV Energy filed the Joint Application pursuant to the Nevada Revised Statutes (“NRS”) and the Nevada Administrative Code (“NAC”) Chapters 703 and 704, including, but not limited to NRS 704.741 et seq. and NAC 704.9005 et seq. Pursuant to NRS 703.190 and NAC 703.527 et seq., NV Energy requests that certain information in the Joint Application receive confidential treatment. 

NV Energy states that the Joint Application demonstrates how it intends to address the State’s clean energy goals and policies and meet the energy demands of its customers by balancing cost, reliability, and decarbonization goals. NV Energy proposes a demand-side management plan to create foundational strategies to enable flexible load and deploy cost-effective Non-Wires Alternatives to support the needs of the grid and the energy needs of the State of Nevada. NV Energy specifically seeks approval to: (1) add three power purchase agreements for solar-generating resources totaling more than 1,000 megawatts (“MW”), each with co-located battery energy storage systems; (2) purchase, install, and operate two company-owned hydrogen-capable natural gas simple cycle combustion turbines; and (3) construct transmission infrastructure necessitated by the new resources and to support growing customer demand. 

Interested and affected persons may file comments or petitions for leave to intervene pursuant to NAC 703.578 through 703.600 electronically through the Electronic Filing System on the Commission’s website or at either of the Commission’s offices on or before WEDNESDAY, JULY 3, 2024. 

A person who wishes to participate as a commenter may file written comments pursuant to NAC 703.491. A commenter is not a party of record and shall not take any action that only a party of record may take. Pursuant to NAC 703.500, only parties of record are entitled to enter an appearance, introduce relevant evidence, examine and cross-examine witnesses, make arguments, make and argue motions, and generally participate in the proceeding. 

NOTICE IS HEREBY GIVEN that, pursuant to NAC 703.655, the Commission has scheduled a PREHEARING CONFERENCE in this docket to be held as follows: 

TUESDAY, JULY 9, 2024 

11:00 a.m. 

Parties will appear and otherwise participate in the prehearing conference remotely via telephone. Members of the public can access the prehearing conference at the time noticed herein via the Commission’s live stream link on its website at https://puc.nv.gov. Parties in this matter must obtain an access code for this telephonic prehearing conference by emailing Commission Administrative Attorney Lindsay Rostron at lrostron@puc.nv.gov no later than FRIDAY, JULY 5, 2024, at 2:00 p.m. Parties should provide the title/role in associated business or organization, and business address for each person who intends to participate in the prehearing conference. 

The purpose of the prehearing conference is to formulate and simplify issues involved in this proceeding and set a hearing and procedural schedule. At the prehearing conference, the Commission may take any action authorized by NAC 703.655. 

The Commission is not responsible for providing clerical or administrative assistance or materials to parties during Commission proceedings. If such assistance is necessary, parties must make other arrangements for this type of assistance. 

The Joint Application is available for public viewing at the Commission’s website: https://puc.nv.gov; and at the offices of the Commission: 1150 East William Street, Carson City, Nevada 89701 and 9075 West Diablo Drive, Suite 250, Las Vegas, Nevada 89148. A person must request in writing to be placed on the service list for this proceeding in order to receive any further notices in this matter. 

By the Commission, 

________________________________ 

TRISHA OSBORNE, 

Assistant Commission Secretary 

Dated: Carson City, Nevada 

6/11/24 

(SEAL) 

Pub dates: June 15, 2024 Ad#44149 rec