REQUEST FOR PROPOSALS
CVSC CONCESSION STORAGE ADDITION & EAST SIDE EXPANSION
Plenium Builders has been selected as the public Construction Manager at Risk (CMAR) and is requesting proposals for the CVSC Concession Storage Addition & East Side Expansion Project.
The project consists of:
• Concession storage addition to the existing mechanical yard.
• Lobby addition with new glazing system and existing lobby
slab to be removed and replaced with new floor drains.
• New storage addition.
• Trades required are selective demolition, CIP, concrete,
masonry, structural steel, rough carpentry, insulation, roofing,
DFH, storefront, metal framing/drywall & acoustic systems,
stucco, tile, flooring, paint, plumbing, HVAC, fire sprinklers,
electrical, earthwork.
• Total approximate budget for construction is $2,600,000.
• Bid documents available May 21, 2024 for qualified
subcontractors.
Proposal Due Date:June 11, 2024
Proposal Due Time:2:00 pm PDT
Proposal Location:Proposals must be delivered in a sealed
envelope to:
Plenium Builders
825 Steneri way
Sparks, NV 89431
Attn: Devin Harrill
775-302-6326
dharrill@pleniumbuilders.com
Project Schedule:
Invitation to Bidders: May 21, 2024
Bids Due: June 11, 2024 @ 2:00pm
Interview: Individually Scheduled
Project Start: September 2024
Project Completion: April 2025
NOTICE: Subcontractors, who will perform at least 1% of the estimated value of the work or $50,000 whichever is greater, must be qualified pursuant to NRS 338.16991. Proposals will be returned to the subcontractor unopened if the subcontractor has not been qualified per NAC 338.580.
Pub Date: May 25, 2024 Ad # 43512